In the face of growing public pressure, the San Jose City Council has enacted a temporary ban on data center projects while the city hammers out new standards to regulate the rapidly growing industry.
La moratoria — approved unanimously Tuesday — means San Jose will pause all land use approvals for data centers as well as other large energy use projects, including the 12 proposed projects under review with the city. It will last until councilmembers finalize the regulatory package for data centers, intended to set minimum benchmarks for things such as energy and water use, air pollution and noise.
As part of Tuesday’s decision, councilmembers also designated the data center development standards as an “urgency ordinance.” As a result, if approved when they go before council on Dec. 8, they will take effect immediately. The standards will first be reviewed by the Planning Commission on Wednesday.
The temporary pause is a response to concern from residents that some pending data center projects might make it through the city’s approval process before the safeguards are in place.
“I am pleased that we’re going to make it clear to our community that nobody will be able to game the system in the next month and be able to avoid having to abide by these standards,” District 4 Councilmember David Cohen said at Tuesday’s meeting.
The authors of the moratorium — including Mayor Matt Mahan and Councilmembers Cohen, Pamela Campos, Peter Ortiz and Domingo Candelas — anunció la medida Nov. 12. It came just days after San José Spotlight reported that Centro de datos de Google in Alviso could be approved ahead of the development standards, a revelation that called into question previous assurances from city leaders that the regulations would be in place before any of the city’s pending projects reached such a milestone.

A chorus of residents who spoke during Tuesday’s meeting argued the moratorium doesn’t go far enough, and urged councilmembers to enact a longer pause to give the city more time to reckon with the potential impacts of the energy and water hungry facilities.
“This item falls short of what the community has been asking for,” Dashiel Leeds, conservation coordinator for the Sierra Club Loma Prieta Chapter, said at the meeting. “And that’s for a moratorium long enough to study the cumulative public health, environmental, climate and financial impacts of these AI data centers.”
Before approving the moratorium, Mahan acknowledged residents’ misgivings, and pledged to continue the policy dialogue.
“I appreciate the deep concern and care and folks being here,” Mahan said. “I want to continue that conversation because ultimately this is about setting a high bar and earning public trust, not rushing something or trying to hide the ball.”
Como titular de nationwide data center buildout has taken shape, San Jose leaders have sought to woo new developments to the city, eager to capitalize on the economic windfall many expect the facilities could bring. But in recent months, as the backlash against the AI-fueled data center boom has hardened, a concerted opposition campaign to block new projects in San Jose has taken shape.
Councilmembers responded to residents’ concerns — which include fears that the electricity demands could drive up power rates and diesel-powered backup generators could pollute the air — by launching the effort to draw up the development standards in June.
Over the following months, angry residents have stormed a series of community meetings held to draw feedback on the proposals, calling for the city to dramatically change course. Among their temas principales has been a demand that San Jose follow the lead of other Bay Area cities — including San Francisco, Oakland y Richmond — in enacting a temporary moratorium on data centers.
Previously, city leaders had resisted such calls, arguing that an immediate moratorium could destabilize the burgeoning technology sector and scare off inversión local. They also said such a pause was unnecessary because no data center project was likely to make it over the finish line before the regulations were put in place.
But last week, city officials confirmed Google’s data center project in Alviso — which the company has referred to as a research and development lab — could come up for approval before the end of the year.
San Jose released the draft data center standards in October. The wide-ranging regulations include requirements that data centers use 100% carbon-neutral electricity, prohibit certain cooling systems that use potable water and set strict limits on the use of backup generators. The measure also imposes labor standards for data center construction projects, and requires developers to pay community impact fees that will fund city priorities such as affordable housing.
Industry groups had staunchly opposed moratorium proposals, but their stance seems to have softened somewhat.
“While some small refinements remain, the standards address community concerns while supporting economic growth here in the heart of Silicon Valley,” Eric McNamara, a spokesperson for the Silicon Valley Leadership Group, which advocates for the high tech industry, said during the meeting. “Today’s temporary pause is a reasonable step toward passing timely and responsible standards on Dec. 8.”
Meanwhile, the unanimous approval left some residents frustrated.
“This almost seems predetermined,” Phil Orselli, a member of Silicon Valley Democratic Socialists of America who was among those calling for a longer pause, told San José Spotlight. “That can be troubling to see when everyone is out there pouring their hearts out, giving compelling facts and figures, but it’s almost as though they’re listening with deaf ears.”
Comuníquese con Keith Menconi a través de [email protected] o @KeithMenconi en X.